QUANTITY SURVEYING  


BOQ

BOQ is aocument use in tendering In the construction industry in which material,parts&labour are itemized.

Advantage of boq

1 we can get the details of the work

2 it can be use evaluate & compare

3 transparancy

4 it will help in planning to the project

Preliminaries

Preliminaries may appeor in tender document, providing & description of a project that almos the contractor to asses cost which, whilist they do not from a part of any of the package of works required by the contract are required by the method &circumances of the work.

A PROVITIONAL SUM

A provitional sum is an allowance usually estimated by a cost consultant, that is inserted into tender document for a specific element of the work that is not yet defined in enough detail for tenders to accurately price

A PRIME COST SUM

A prime cost sum is allowance, usually calculated by the cost consultant for the supply of work material to be provide by a contractors to suppler that will be nominated by  the client.

TENDERING

Tendering usually refer to the prcess where by government & financial institution invites bid for large  project that must be submitted within a finite deadline the term also refer to the process whereby shareholders submit their shaers or securities response to a takeover offer.

Tender evaluation

Tender evaluation is a process that select the lowest suitable bidder to the construction project in correct manner.

Pre bid meeting

Pre bid meeting are gathering shedules after an invitation to bids or request for proposals is advertised.they are called pre meeting because they are pertinent to procurement of goods ,non consultantservise& works

Fluctuation

Fluctuation is a change or variation in a quantity over time.

Subcontractor

A ferm or person that carries out work for a company as part of a larger project.

Procurement

Procurement is process of finding &agreeing  to terms & acquiring goods, service or work from an external source of a tendering or competitive biddibg process.

 

 

Bonds in construction industry

1 bid bond     2 performance bond                      3 mobilization advance bond

Documents of including in to tender

1 invitation to bid        2 bidding data

3  BOQ                       4 form of tender

5 specification & drawings

Value management &value engineering

Value management &value engineering are techniques concerned with defining , maximizing &acheiving a value for money value management provide an exceptionally powerful tool to explore a project’s objectives & aspiration from the client’s perspective.

Variation

A variation is an alternation to the scope of work  in a construction contract in a form of an addition , substitution amissing from the original scope of work.

Bid security 

A bi security is an amount of money that may be calculate as a percentage of the budget estimate of a procurement requirement or a percentage of a bider’s bid price it gives the client some assurance that the selected bidder sign the contract or other wiseforfit their bid security.

Interim certificates

Interim certificate provide a mechanisumfor the client to make payments to the contractor before the work are complte.

Methods of measurement

1 direct method

2 indirect method

3 comparative method

4 contract method

5 deflection method

Preamble

Preamble is an explanation of a documents commonly found in contracts, specification & bill of quantities. It can help with the interpretation of the document. A preamble might include a description of the parties to the contract.

Overhead

Overhea expenses are all cost on the income statement except for direct labour, direct materials & direct expenses. Overhead expenses include accounting fees, advertising, insurance, interest,legalfees,labour burden, rent &ect.

Day work in construction

Day work is a mean by which a contractor is paid for specially instructed work on the basis of the cost of labour, materials & plant a mark up for overhead & profit. It is generally use when work cannot be price in the normal way.

 

Interim certificate

provide a mechanism for the client to make payments to the contractors before the work are complete

Retention

is the percentage of the amount certified as due to the contractor on an interim certificate. that is deducted from the amount due and retained by the client the purpose of retention is to ensure that the contractor properly completes the activities required of them under the contract

Limit of retention

 5% of initial contract some. release 2.5 % of completion bill.

Material at site there are currently used available raw materials required for construction in the site that are called materials at site.80% of material at site include interim bill.

Defect liability period is a set of period of time after a construction project has been completed during which a contractor has the right to return to the site to remedy defects

The mobilization  advance

is a monetary payment by the client to the contractor for initial expenditure in respect of site mobilization and fair proportion of job overheads preliminaries. mobilization advance payment reduces contractor need for working capital.

Contingency some

is an amount of money, usually expressed as a percentage, included in the project budget to allow for unknown or unsolved aspect of a design. it's usually for the initial allowance to be much as to 25% to 30%

extra over

is term that is often used when taking off from a bill of quantities when taking off for a BOQ, the term "extra over"can be used to refer to items that to a certain extent have already been measured, but have not been priced at the full value of all their labour and material.

additional work

situation where a contractor performs additional work under a construction contract occur often in practice.A contractor includes a contract for construction with a customer, the term of which establishe that he will receive a fixed sum in return for the completion of certain amount of work

extra work

is something that is done in addition to the requirement of the Contract.A contractor is generally entitled to change for extra work the consists of labour material not contemplated by or subsumed within the original contract

 

 

 

 

SLS 573  SMMS

SLS 573-Sri Lanakan standards

SMM 3-Civil engineering works (roads & other works) few items large quantities.

8. items largwg works(roads & other works)few items largw quantities.All in plant rate,

A rate which includes the cost originating from the ownership or hire of plant together with operating cost.

Head office over heads

recovery of contractors head office over heads, one of the less understood elements in construction damage.claim is the head office overhead that in incurred when a project is delayed . however it is compensable and there is no doubt that head office overhead is an entitled expense of the contract

Lump sum contract is the traditional means of procuring construction, and still the most common form of construction contracts. under a lump sum contract, a single lump sum price for all the work is agreed before the works begin.

* involves a total fixed priced for all construction related activities.

* can include incentives of benefit for early termination damages, for a late termination

Measure & pay contract,

this contract format is generally used for construction works contract rather than services contracts. during the construction period,the actual quantity of work executed under each BOQ items will be jointly measured and valued at the quated rate for interim payment purpose.

*After remeasure valued at the quated rate for evaluate the final account

Work method statement

is a document that details the way a work task or process is to be completed.the method statement should outline the hazards involved and include a step-by-step guide on how to do the job safely.

Down time-period during which an equipment or machine is not functional or cannot work. it may be due to technical failure machine adjustment, maintenance or non availability of input such as materials, labour,power.

Attendance

is the contractors markup for specific service it has to provide for individual suppliers or subcontractor. this might include items such as material handling, scaffolding and rubbish clearance

the approximate estimate

is done in order to find out an approximate cost in very short time before starting the project the estimate is made before selecting the final specification and design of the project.this method is also known as preliminary or rough estimate

 

 

 

Site visit process

and schedule the purpose of the site visit evaluation is to obtain in depth information concerning all administrative and educational aspect of the program

Trade discount is one that is allowed by the wholesaler to the retailer, calculated on the list price of the product

extension of time construction contracts generally allow the construction period to be extended where there is a delay that is not the contractor's fault. this is described as an extension of time

A bid bond is debt Secured by a bidder for a construction job, or similar type of bid based selection process, for the process of providing a guarantee to the project owner that the Builder will take on the job if selected

A performance bond is commonly used in the construction industry as a means of insuring a client against the risk of a contractor failing to fulfill contractual obligations to the client. performance Bond can also be required from other parties to a construction contract

Markup-Somewhere along the line,people started believing that a 10% overhead & 10% profit is the industry started for construction jobs.or that a 20% markup is all a contractor needs.

contract is a legal binding agreement between two or more parties.