Methods of Tendering
The
Owner / Client / Employer has some choices in its approach to selecting a
contractor. Will any and all interested contractors be permitted to submit
proposals? Will the list be limited to a selected group of contractors, and, if
so, how will the list be identified? Will the owner negotiate with only a
single contractor? Will some sort of pre-qualification or post-qualification be
used?
Tendering
Tendering is the name
given to the process or procedure
that is used to obtain offers leading to a contract between a client and
contractor, a client and consultant, a contractor and subcontractor,
and so on. Before starting the tendering process, a decision will need to have
been made, on the contract arrangements that will have to be entered into on
acceptance of a tender. Therefore 'tendering' and a 'contract' are clearly
distinguishable in concept. But they are very closely linked in practice.
Pre-qualification
/ Post-qualification
Prequalification is normally applied for large civil works, industrial projects,
major equipment and supply acquisition,
specialized services and contracts to be let under turnkey, design and build,
or management contracting. This assures
that only firms capable financially, technically and with experience will
submit bids. This increases procurement lead-time considerably.
Therefore it is not advisable to use this procedure for simple procurement
works.
Objectives that could be achieved through
Pre-qualification;
a. Assure the owner that bidder has the technical / financial / managerial background with experience to perform the contract successfully.
b. Allow unqualified bidders to avoid bid preparation cost.
c. Assures leading contractors that only qualified contractors will submit bids.
d. Prevent unqualified bidders from wining the bid.
e. To limit the number of bidders to a manageable size for conducting the bidding procedure and evaluation process.
f.
To enable
prospective bidders, who may be insufficiently qualified on their own, to form
a joint venture that may give them a better chance of success.
Principle factors that are
being used to measure the qualification of an applicant for pre-qualification -
Information requested under pre-qualification procedure;
1 Financial capacity
2
Technical capacity
3
Relevant experience
Financial capacity
a.
Average annual income from contracting
at least in last 3 years
b.
Bid
capacity (Total assets and total liabilities / approximate value in hand /
balance sheet / P & L statement)
c.
Available credit
d. Site
management - Project organization & management, Sub contracting
e. Key
technical personnel and Project Manager (organization chart & CVs)
f. Plant
& Equipment
Experience Experience
as main contractor / lead partner, Experience with similar works, Experience
with similar site conditions, Past performance (List of completed projects with
name of the
employer/ location/ type of project and
all projects in hand).
Post-qualification -
If a contractor is the apparent low tenderer for a project,
then he will be asked to submit information
demonstrating its qualifications submitted with the tender. If he can prove his
qualifications, then the contract will be awarded to him. If not, the client
has two options, either to go for the second lowest or re-tender, depending on
the situation. The major disadvantage is, if the first contractor found
unsuitable, then effort throughout the tender process for selecting him is
wasted. The rejected tenderer may also claim that he unjustly rejected as not
qualified for favouring some other tenderer. However, owners do have the right
to choose ‘responsive’ and ‘responsible’ tenders, according to all well-written
contract documents. There is always the chance for claims of unfairness when
the owner decides whether a contractor’s tender is ‘responsible’.
In
most cases, an open pre-qualification
process would appear to be the fairer method for all concerned. Certainly
pre-qualification requires contractors to meet only a minimum level of
qualification. In evaluating tenders, owners can then rank contractor
qualifications according to specified criteria in deciding which one of the
qualified contractors to select.
There
are three principal methods for choosing a contractor:
(a) Open tendering,
(b) Selective tendering,
(c)Nomination
Open
tendering
Open
tendering is a procedure of allowing any eligible organization, probably
following advertisement(s) to submit a tender. Open tendering will secure
maximum competition by giving any organization an opportunity to tender.
Major
disadvantage in this practice is it can lead
to organizations tendering that do not have adequate resources and/or expertise
of the work. If there is no pre-qualification
requirement, then any interested eligible contractors are allowed to submit
tenders. An invitation to tender is issued, and tenders are received and
evaluated. Usually a deposit is required to discourage irresponsible
applicants. Normally, the deposit is returnable on the submission of the bid.
If the criteria for selection are based on price alone, the owner must decide
whether the
low
bid is both ‘responsive’ to the tender announcement and ‘responsible’. It means
that the contractor is qualified to do the work. If criteria in addition to
price are used to judge the tender, then measurements of qualification will be
a part of this process. In either path, the end result will be an agreement
with a qualified contractor.
This
process is initiated by client advertising in newspapers and / or inviting
contractors to apply for bid documents and to bid in competition for carrying
out the work.
|
Advantages |
– There can be no favoritism / can
get the maximum benefit from competition / an opportunity |
|
|
|
|
is provided for any capable firm. |
|
Disadvantages |
– There is a danger that a firm
inexperienced in preparing bids may submit the lowest bid / |
|
|
|
|
there is no guarantee that the lowest
bidder is sufficiently capable or financially stable / total |
|
|
|
cost of bidding is increased. |
Selective
Tendering
Selective
tendering is a process or procedure for selecting a limited number of firms
and then inviting them to tender. Selective tendering is a
recommended method where competition is wanted.
Initially,
a short list of contractors who are considered to be suitable to carry out the proposed
work is prepared. Names may be selected from an approved list or ‘panel’
maintained by the client. It is recommended that the number of bidders should
be limited to a manageable number, depending on the size of the contract. If
the firms on the list are all reputable, well established and suitable for the
proposed work, then the selection is resolved into a question of price only.
|
Advantages |
– Ensures that only capable and
approved firms submit bids / reduce the cost of bidding. |
|
|
|
|
|
|
Disadvantages |
– Cost level of
the bids will be higher due to less competition and also due to the higher
caliber |
|
|
of the bidders. |
|
|
Once
the tenders are received, they are evaluated in a manner similar to those
received though the open tender process.
Another
version of the invited tender, sometimes used in the private sector, involves
the owner, or its design professional, in inviting tenders from firms it
believes to be qualified, based on their reputations, past experience and other
criteria. This approach is probably not appropriate in the public sector, where
accountability to public requires credibility and transparency.
Nomination –
Sometimes referred as ‘single tendering’.
It is a special case of selective tendering where the short list has only
one name. Used when the client has a preference for a particular
firm, often because it has done satisfactory works for him before. In this
method, competition is eliminated and that will lead to a higher price.
Contract sum will be arrived by a process of negotiations. When a large project
is to be carried out in successive phases, a combination of selective tendering
and nomination is employed – this is sometimes called “serial tendering”.
Serial
Tendering
- 'Serial tendering' is the term used where tenders are invited
for a project or series of projects, each
of which will become a contract or contracts in their own right. The contractor
is chosen for the first phase by means of selective or open competitive
tendering. The accepted tender outlines the basis of payment for the resulting
contract. The tender is also used for the second and later phases. However, a
provision has to be made for so doing in the initial contract by the inclusion
of a formula for updating prices. The purpose of serial tendering is to gain the
benefits of continuity.
The contractor for the first phase of the project will have his site
organization set up, his offices and storage huts, etc., already in use and
plant of various kinds on the site. When the second phase commences, these
facilities will be already available. It allows smooth transition with less
additional expenses. In addition, the contractor’s workforce will be familiar
with the details of the construction after building the first phase, and it
helps to work more speedily and efficiently.
Negotiated Contracts
This
may be done using bills of quantities / schedules of rates. The rates and
prices are discussed and agreed until eventually a total price is arrived.
Usually negotiation will be conducted between the contractor’s quantity
surveyor and the project quantity surveyor. One party will usually price the
tender document first of all, and then the other party goes through the rates
and prices ticking off those which are acceptable. When agreement is reached, a
contract will be entered between the client and the contractor. This process is
sometimes called Single stage negotiation. In this procedure,
absence of competition usually results in a higher price. Therefore, with a view to gaining the benefits of
competition as well as the advantages of negotiation, a process of limited
competition for the selection of contractor, followed by negotiation with him
on the details of his tender, is used. This process is usually known as two-stage negotiation.
In the first stage tenderers are
informed of the second stage intention and are asked to tender on the basis of
Schedule of rates consisting of the main/ significant items only.
- Prices for the main preliminary items.
- Construction program showing estimated times.
- Labor and plant resources/ construction methods.
-
Details
of all labor rates / material prices / discounts, etc.
Discussion with each of the tenderers
may be conducted in order to clarify their proposals. Having selected a
contractor at the end of the competition stage, negotiation will follow on the
basis of a detailed tender document as in single stage negotiation.
Two-stage
negotiation is the method normally used to select a contractor to carry out management contract, in which the
general contractor does little or none of the construction work himself but
organizes sub-contractors to do the work.
Negotiation
is a skilled process and requires skilled clients, consultant advisers and
contractors and those participating in it should be adequately trained and
experienced.

0 Comments